The Bloomfield Township Public Library at 1099 Lone Pine Road is open this November. The construction walls block off the Youth Room, the Magazine Room, the Vending Café and the Commons, which are the spaces built for spending an afternoon. Everything on the shelves can still be browsed and checked out. Holds can still be picked up without leaving your car. The chamber concerts, story times and book clubs are still on the calendar. From now until the end of January, the library works best for short visits and evening events, and the stretch of the project that changes that comes next.
The Walls Went Up Around the Rooms Where People Stay
The library's last renovation was nearly 20 years ago. The current project began in late August 2026 and is expected to finish in summer 2027. The work is split into three phases, and temporary walls move through the building as each phase starts:
- Phase 1, late August 2026 to late January 2027: Youth Services, the Welcome and Circulation desks, the Commons, the magazine room, and parts of Adult and Teen Services.
- Phase 2A, late January to early May 2027: the north end of the building, from about the atlas stand through the study rooms and the Computer Lab.
- Phase 2B, early May through July 2027: most of Adult and Teen Services, including its service desk.
The library notes that these dates may change. Phase 1 has taken the spaces where visitors sit, read and meet. The October e-newsletter says seating is limited for now and so is access to power outlets. Meeting rooms have been out of public use since September because the library needs them to keep running during construction. The entire Youth Services collection was moved out of the Youth Room, according to the library board's September meeting record. When collections are relocated, the library says staff will be there to help you find materials.
Behind the walls, the work has moved quickly. The October 16 progress update reported interior demolition complete. By October 23, interior wall framing was finished, electrical rough-ins were underway and drywall had started in some areas. Next on the list were drywall ceilings, new floor boxes and concrete infill at the floor openings. The library posts these updates weekly as short slide decks on the renovation page.
The Quick Visit Still Works, and Curbside Is Faster
Losing the lounge space matters much less if your errand is picking up holds. Curbside pickup follows a short routine:
- Wait for the email saying your hold is ready.
- Park on the east side of the lot, near Timberlake Road.
- Call 248-642-5800.
- Stay in your car while staff bring the items out.
If you're planning a pickup close to opening or closing time, call ahead. The posted library hours are 9:30 a.m. to 9 p.m. Monday through Thursday, 9:30 a.m. to 6:30 p.m. Friday, 9:30 a.m. to 5:30 p.m. Saturday and noon to 5:30 p.m. Sunday.
If you'd rather go in, everything is still available to browse and check out. Ask at the desk instead of searching the stacks yourself.
The Calendar Through New Year's
The library is offering fewer programs during construction. It has kept story times, book clubs, discussion groups and the Chamber Music Concert series. The October newsletter also lists the English Language Conversation Group and the Movie Discussion Club among adult services. These are the dates to note between now and the end of the year:
| Date | What's happening |
|---|---|
| Saturday, Nov. 7 | Teen Craft Club, noon to 2 p.m. |
| Wednesday, Nov. 11 | Library closed for Veterans Day and a Staff Development Day |
| Thursdays, Nov. 12 to Dec. 10 | Toddler story time, 10:30 a.m. |
| Fridays, Nov. 13 to Dec. 11 | Toddler story time, 10:30 a.m. |
| Saturday, Nov. 14 | Friends of the Library Second Saturday Sale, lower level |
| Wednesday, Nov. 25 | Library closes at 5:30 p.m. |
| Thursday, Nov. 26 | Closed for Thanksgiving |
| Friday, Dec. 11 | Chamber Music Concert, 7 to 8:30 p.m. |
| Thursday and Friday, Dec. 24 and 25 | Closed for Christmas |
| Thursday, Dec. 31 | Library closes at 5:30 p.m. |
| Friday, Jan. 1 | Closed for New Year's Day |
The Friends' sale on November 14 takes place downstairs, away from the construction. Friends members can shop from 10 to 11 a.m., and the sale opens to everyone from 11 a.m. to 3 p.m. Cash and debit are accepted for any amount, credit cards need a $5 minimum, and you can buy a Friends membership at the door if you want the early hour, according to the library's October 28 announcement.
The Evening Concerts Run Through the Rest of the Project
The Chamber Music Concert series is one of the programs the library is keeping during construction. Student musicians from the University of Michigan School of Music, Theatre & Dance perform, and the program for each concert comes out the week before. The December 11 concert runs from 7 to 8:30 p.m. and doesn't require registration.
The series continues into Phase 2. The January 8 concert runs from 7 to 9 p.m. The February 19 and March 5 concerts both run from 7 to 8:30 p.m. The library board's October 20 packet also lists April 9 as a concert date. These evenings are the one part of the library calendar that construction hasn't cut back. The renovation team expects some noise and dust as work continues.
Late January Is the Date to Watch
When Phase 1 ends, the walls move to the north end of the building. That's where the study rooms and the Computer Lab are. The library has already said that study rooms may be closed during some phases. If you're counting on a quiet room for exam season or remote work in February, plan on the current setup changing.
The changeover itself may also mean a short closure. In its October 20 meeting, the library board said it expects "another two-week closure to move the shelving back, install furniture, and move the temporary walls" between Phase 1 and Phase 2. That comes from the board packet, and it's a planning estimate. If you have holds or due dates near the end of January, the weekly updates on the renovation page are where the actual dates will be posted.
What Comes Back When the Walls Come Down
The rooms closed this winter are also the ones getting the biggest changes. The project plan includes:
- Holds moved to the front of the library, with public computers and printers moved nearby
- A coffee-shop feel for the magazine room
- Five new study rooms
- A sensory room, a lactation room and two wellness rooms
- A new programming room for adults and teens
- A more flexible Computer Lab, plus service desks moved to improve service and sightlines
- New furniture, carpet and paint throughout the public areas
The team behind the work includes architects and interior designers from C2AE and Jenna Walker of Reed Walker Design Collective. Walker led the early design research and then schematic design, shaping the floor plans, finishes and furniture choices. McCarthy & Smith is managing construction, and Library Design Associates is planning the phasing and moves that keep collections and seating available while the work goes on. Questions go to Library Director Tera Moon at [email protected].
When the holds shelf moves to the front, the library will have built into the floor plan the kind of quick visit that curbside pickup supports right now.
We keep an eye on Township projects like the library renovation along with the market. If the year ahead has you thinking about your own home, Meredith Colburn and our team can tell you where it stands today. Get a free home valuation whenever you're ready.